15 Bayview Rd

Variation control

Risk register

Priority risks to close out before signing a domestic building contract.

Priority risks

Priority #1

7-star / SDA / thermally broken glazing

High

Exposed builders

Bevnol, Aspire, Symmetric, Chet confirmation needed

Likely cost

Medium to high

Mitigation

Require written confirmation that final energy report, NCC 2022 and SDA obligations are included as fixed price.

Priority #2

Drainage / OSD / WSUD / LPOD

High

Exposed builders

Bevnol, Aspire, Symmetric

Likely cost

High

Mitigation

Require itemised drainage inclusion list covering OSD, orifice, pits, pipes, raingardens, LPOD and council inspections.

Priority #3

Landscaping and fencing

High

Exposed builders

Bevnol, Aspire, Symmetric

Likely cost

$30k-$90k+

Mitigation

Obtain fixed separate price or carry owner contingency.

Priority #4

TPMP / arborist / tree protection

High

Exposed builders

Bevnol, Aspire, Symmetric, Chet confirmation needed

Likely cost

Medium to high

Mitigation

Confirm project arborist, fencing, ground protection, inspections and final certification.

Priority #5

Driveway / crossover / reinstatement

High

Exposed builders

Bevnol, Aspire, Symmetric

Likely cost

$10k-$35k+

Mitigation

Require specific scope for driveway, crossover, footpath/kerb reinstatement and asset protection.

Priority #6

Sewer diversion / branch / depth

High

Exposed builders

Bevnol, Aspire, Symmetric

Likely cost

$8k-$35k+

Mitigation

Confirm branch, depth >1.5m, existing dwelling continuity and service proving.

Full register

Contract clarification priority list

#RiskExposed buildersLikely costMitigationLevel
#17-star / SDA / thermally broken glazingBevnol, Aspire, Symmetric, Chet confirmation neededMedium to highRequire written confirmation that final energy report, NCC 2022 and SDA obligations are included as fixed price.High
#2Drainage / OSD / WSUD / LPODBevnol, Aspire, SymmetricHighRequire itemised drainage inclusion list covering OSD, orifice, pits, pipes, raingardens, LPOD and council inspections.High
#3Landscaping and fencingBevnol, Aspire, Symmetric$30k-$90k+Obtain fixed separate price or carry owner contingency.High
#4TPMP / arborist / tree protectionBevnol, Aspire, Symmetric, Chet confirmation neededMedium to highConfirm project arborist, fencing, ground protection, inspections and final certification.High
#5Driveway / crossover / reinstatementBevnol, Aspire, Symmetric$10k-$35k+Require specific scope for driveway, crossover, footpath/kerb reinstatement and asset protection.High
#6Sewer diversion / branch / depthBevnol, Aspire, Symmetric$8k-$35k+Confirm branch, depth >1.5m, existing dwelling continuity and service proving.High
#7Aspire carport scope gapAspire$15k-$50kAsk Aspire to confirm the 33.5m2 carport is included or provide variation price.High
#8Chet labour/subtotal reconciliationChetApprox. $87k incl. GSTRequest corrected BOQ and subtotal reconciliation before comparing.High
#9Structural PS despite available engineeringAspire, Symmetric, Bevnol confirmation neededMediumAsk builders to price from KCE structural drawings rather than broad allowances.Medium-High
#10Authority/service costsAll buildersMediumClarify power pit, water meter, NBN, asset protection, tapping permits and connection activation fees.Medium-High