15 Bayview Rd

Quote audit

Quote matrix

Every builder quote reconciled against source-library requirements. Do not treat an item as included unless the quote expressly states it.

Source-library requirements

Status: Included · Excluded · Provisional Sum · Prime Cost · Unclear · By Owner · Variation Risk

RequirementQuote item to checkBevnolAspireSymmetricChetRisk

212.7m2 dwelling

Working drawings and quotes reference the same 212.7m2 total building area.

Dwelling size and base build scopeIncludedIncludedIncludedIncludedLow

33.5m2 carport

Working/source drawings include a proposed 33.5m2 carport.

Carport structure, roof, posts, slab/base and drainageIncludedUnclear / likely missingIncludedUnclear unless BOQ confirmsHigh for Aspire

Pergola / alfresco

Working drawings include pergola/alfresco area.

Pergola roof/framing/slab/lighting/finishesIncludedIncludedIncludedUnclear unless BOQ confirmsMedium

Landscaping before occupation

Planning/source library flags landscaping/external works as occupation/compliance issue.

Landscaping, lawns, garden beds, planting, watering, external completionExcludedBy Owner / ExcludedUnclear / likely not adequateProvisional SumHigh

TPMP / arborist / tree protection

TPMP requires project arborist, fencing, ground protection, inspections, supervision and final certification.

Tree protection fencing, project arborist, inspections, ground protection, tree-sensitive excavationVariation RiskBy Owner / UnclearUnclear / ExcludedUnclearHigh

Drainage / OSD / WSUD / LPOD

Approved drainage plans require OSD/orifice pit, pipe storage, pits, charged rainwater tank downpipes, raingardens, permits and final inspection.

Tank, pits, pipework, OSD, orifice, rain gardens, LPD connection and council tapping/new pit riskVariation RiskProvisional SumVariation RiskProvisional Sum / stronger allowanceHigh

SDA / 7-star / NCC 2022

SDA/energy documents require 7-star/NatHERS, whole-of-home energy, heat pump systems, WELS fixtures, LED lighting and completion report.

7-star energy, whole-of-home, appliances, glazing, WELS, lighting, SDA certificationVariation RiskVariation RiskVariation RiskUnclearHigh

Double glazing / glazing spec

SDA and energy pathway require double glazing; final drawings/energy schedule may require specific glazing performance.

Double glazing, Low-E, thermally broken frames, window sealsVariation RiskProvisional SumVariation RiskUnclearHigh

KCE structural design

Structural drawings/compliance certificate exist and must be priced.

Slab, footings, steel/LVL beams, bracing, posts, retaining, carport structural itemsUnclearProvisional SumUnclearIncluded / clearerMedium-High

Retaining

Retaining must suit site levels and structural/civil requirements.

Retaining wall length, height, footing, drainage and boundary conditionsIncluded / limitedProvisional SumExcluded / UnclearUnclearMedium-High

Driveway / crossover / reinstatement

External access must be all-weather, drained and completed to council requirements.

Driveway, crossover, footpath/kerb reinstatement, asset protectionUnclearBy Owner / ExcludedVariation RiskIncludedHigh

Sewer / service proving and diversion

Asset/service locations must be proven by hand; diversion/branch/depth and existing dwelling services need fixed-price clarification.

Sewer diversion, branch alteration, depth >1.5m, existing dwelling continuityVariation RiskProvisional SumUnclearUnclear / stronger allowanceHigh

Electricity pit / meter / services

New/changed service connections on subdivided block must be clarified.

Electricity pit, group metering, mains switchboard, NBN, water meters, activation feesBy Owner / Variation RiskBy Owner / Variation RiskBy Owner / Variation RiskUnclearMedium-High

Livable housing

Livable housing requirements include step-free access, door/corridor clearances, sanitary circulation, hobless shower and reinforcement.

NCC livable housing complianceUnclearUnclearUnclearUnclearMedium