15 Bayview Rd

Builder rank #1

Bevnol

Best current balance of price and source-library coverage, but acceptance should be conditional on written fixed-price clarification for energy/glazing, drainage/WSUD, trees, driveway/crossover, sewer/services, landscaping and fencing.

Quote snapshot

Risk-adjusted view, not just headline price.

Price

$677,526

Cost/m²

$3,185

PC/PS

$2,640

Confidence

Medium-High

Likely finished band

$750,000$810,000

MediumPreferred - clarify before signing
78/100

Assessment

Strengths, risks and next actions based on the source document library.

Strengths

  • Includes 212.7m2 dwelling scope.
  • Clearly includes the 33.5m2 double carport.
  • Building permit and builders warranty insurance are noted as included.
  • Traffic management is noted as included.
  • Rain garden, sewer/stormwater to LPD and 3000L tank are noted as included.
  • Ducted heating/cooling, solar, pergola, shed, clothesline and letterbox are noted as included.

Risks

  • 7-star wording remains in tension with exclusion of Low-E and thermally broken glazing.
  • Landscaping and internal/external fencing are excluded.
  • Driveway wording is vague and does not clearly cover crossover/reinstatement.
  • Sewer wording conflicts between diversion included and sewer branch/depth exclusions.
  • Tree protection fencing is noted, but arborist/tree management/report/approval items are excluded.
  • Rock, bored piers, suspended slabs and angle of repose works are excluded.

Actions

  • Ask for a source-library compliance response using Included/Excluded/PS/PC/By Owner status.
  • Confirm full approved drainage, OSD, WSUD, rain garden, tank, orifice and LPOD scope.
  • Confirm final glazing system and 7-star/NCC 2022 compliance with no post-contract variation.
  • Clarify driveway, crossover, footpath and council reinstatement scope.
  • Clarify sewer branch, sewer depth and service rectification limits.
  • Price landscaping, fencing and TPMP/arborist supervision/certification.

Exclusions and owner-cost risks

ItemStatusRealistic estimateRisk
Landscaping

Must be priced separately or carried as owner contingency.

Excluded$40,000High
Internal/external fencing

Could interact with TPZ requirements and neighbour boundary works.

Excluded$15,000High
Low-E / thermally broken glazing

Needs direct written confirmation against the final energy report.

Excluded / Variation Risk$20,000High
Driveway/crossover/reinstatement shortfall

Bevnol's driveway wording is not enough to confirm crossover/reinstatement.

Unclear / Variation Risk$20,000High
Tree/arborist supervision and certification

Tree fencing does not equal full TPMP compliance.

Excluded / Variation Risk$6,000High
Sewer branch/depth/service rectification

Clarify branch alteration and connections deeper than 1.5m.

Excluded / Variation Risk$15,000High
Rock / bored piers / angle of repose

Conditional risk; do not carry high unless triggered.

Excluded$20,000High

PC / PS items

ItemTypeAmountRisk
NBN provisioning

Owner remains responsible for network connection/activation cost.

PS$2,640Low-Medium

Quote-vs-source requirements for Bevnol

Shows status against each core source-library requirement.

RequirementStatusQuote item to checkRisk
212.7m2 dwelling

Working drawings and quotes reference the same 212.7m2 total building area.

IncludedDwelling size and base build scopeLow
33.5m2 carport

Working/source drawings include a proposed 33.5m2 carport.

IncludedCarport structure, roof, posts, slab/base and drainageHigh for Aspire
Pergola / alfresco

Working drawings include pergola/alfresco area.

IncludedPergola roof/framing/slab/lighting/finishesMedium
Landscaping before occupation

Planning/source library flags landscaping/external works as occupation/compliance issue.

ExcludedLandscaping, lawns, garden beds, planting, watering, external completionHigh
TPMP / arborist / tree protection

TPMP requires project arborist, fencing, ground protection, inspections, supervision and final certification.

Variation RiskTree protection fencing, project arborist, inspections, ground protection, tree-sensitive excavationHigh
Drainage / OSD / WSUD / LPOD

Approved drainage plans require OSD/orifice pit, pipe storage, pits, charged rainwater tank downpipes, raingardens, permits and final inspection.

Variation RiskTank, pits, pipework, OSD, orifice, rain gardens, LPD connection and council tapping/new pit riskHigh
SDA / 7-star / NCC 2022

SDA/energy documents require 7-star/NatHERS, whole-of-home energy, heat pump systems, WELS fixtures, LED lighting and completion report.

Variation Risk7-star energy, whole-of-home, appliances, glazing, WELS, lighting, SDA certificationHigh
Double glazing / glazing spec

SDA and energy pathway require double glazing; final drawings/energy schedule may require specific glazing performance.

Variation RiskDouble glazing, Low-E, thermally broken frames, window sealsHigh
KCE structural design

Structural drawings/compliance certificate exist and must be priced.

UnclearSlab, footings, steel/LVL beams, bracing, posts, retaining, carport structural itemsMedium-High
Retaining

Retaining must suit site levels and structural/civil requirements.

Included / limitedRetaining wall length, height, footing, drainage and boundary conditionsMedium-High
Driveway / crossover / reinstatement

External access must be all-weather, drained and completed to council requirements.

UnclearDriveway, crossover, footpath/kerb reinstatement, asset protectionHigh
Sewer / service proving and diversion

Asset/service locations must be proven by hand; diversion/branch/depth and existing dwelling services need fixed-price clarification.

Variation RiskSewer diversion, branch alteration, depth >1.5m, existing dwelling continuityHigh
Electricity pit / meter / services

New/changed service connections on subdivided block must be clarified.

By Owner / Variation RiskElectricity pit, group metering, mains switchboard, NBN, water meters, activation feesMedium-High
Livable housing

Livable housing requirements include step-free access, door/corridor clearances, sanitary circulation, hobless shower and reinforcement.

UnclearNCC livable housing complianceMedium