{"exportedAt":"2026-05-08T16:01:41.184Z","builders":[{"id":1,"slug":"bevnol","name":"Bevnol","price":677526,"cost_per_m2":3185,"audit_rank":1,"risk":"Medium","transparency":"Medium","ps_pc_exposure":2640,"likely_low":750000,"likely_high":810000,"plan_fit_score":78,"confidence":"Medium-High","status":"Preferred - clarify before signing","summary":"Best current balance of price and source-library coverage, but acceptance should be conditional on written fixed-price clarification for energy/glazing, drainage/WSUD, trees, driveway/crossover, sewer/services, landscaping and fencing."},{"id":3,"slug":"aspire","name":"Aspire","price":615752,"cost_per_m2":2895,"audit_rank":3,"risk":"Medium-High","transparency":"Medium","ps_pc_exposure":128900,"likely_low":700000,"likely_high":820000,"plan_fit_score":58,"confidence":"Medium-Low","status":"Competitive - requires reprice","summary":"Attractive headline price, but the source library exposes major provisional sums, external work exclusions and a likely carport gap."},{"id":4,"slug":"symmetric","name":"Symmetric","price":582998,"cost_per_m2":2741,"audit_rank":4,"risk":"High","transparency":"Low-Medium","ps_pc_exposure":null,"likely_low":680000,"likely_high":780000,"plan_fit_score":50,"confidence":"Low-Medium","status":"Cheapest - highest uncertainty","summary":"Lowest headline price, but the highest source-document mismatch and variation risk. It should not be relied upon without a revised fixed-price response to the source library."}],"matrix":[{"id":1,"requirement":"212.7m2 dwelling","source_requirement":"Working drawings and quotes reference the same 212.7m2 total building area.","quote_item_to_check":"Dwelling size and base build scope","risk_level":"Low","notes":"All current quotes broadly align on building area.","bevnol":"Included","aspire":"Included","symmetric":"Included","chet":"Included"},{"id":2,"requirement":"33.5m2 carport","source_requirement":"Working/source drawings include a proposed 33.5m2 carport.","quote_item_to_check":"Carport structure, roof, posts, slab/base and drainage","risk_level":"High for Aspire","notes":"This must be expressly included; do not assume it is part of base build.","bevnol":"Included","aspire":"Unclear / likely missing","symmetric":"Included","chet":"Unclear unless BOQ confirms"},{"id":3,"requirement":"Pergola / alfresco","source_requirement":"Working drawings include pergola/alfresco area.","quote_item_to_check":"Pergola roof/framing/slab/lighting/finishes","risk_level":"Medium","notes":"Some quotes mention pergola but final scope should match drawings.","bevnol":"Included","aspire":"Included","symmetric":"Included","chet":"Unclear unless BOQ confirms"},{"id":4,"requirement":"Landscaping before occupation","source_requirement":"Planning/source library flags landscaping/external works as occupation/compliance issue.","quote_item_to_check":"Landscaping, lawns, garden beds, planting, watering, external completion","risk_level":"High","notes":"This is a major hidden cost where excluded.","bevnol":"Excluded","aspire":"By Owner / Excluded","symmetric":"Unclear / likely not adequate","chet":"Provisional Sum"},{"id":5,"requirement":"TPMP / arborist / tree protection","source_requirement":"TPMP requires project arborist, fencing, ground protection, inspections, supervision and final certification.","quote_item_to_check":"Tree protection fencing, project arborist, inspections, ground protection, tree-sensitive excavation","risk_level":"High","notes":"Tree fencing alone may not satisfy the TPMP.","bevnol":"Variation Risk","aspire":"By Owner / Unclear","symmetric":"Unclear / Excluded","chet":"Unclear"},{"id":6,"requirement":"Drainage / OSD / WSUD / LPOD","source_requirement":"Approved drainage plans require OSD/orifice pit, pipe storage, pits, charged rainwater tank downpipes, raingardens, permits and final inspection.","quote_item_to_check":"Tank, pits, pipework, OSD, orifice, rain gardens, LPD connection and council tapping/new pit risk","risk_level":"High","notes":"Generic stormwater wording is not enough.","bevnol":"Variation Risk","aspire":"Provisional Sum","symmetric":"Variation Risk","chet":"Provisional Sum / stronger allowance"},{"id":7,"requirement":"SDA / 7-star / NCC 2022","source_requirement":"SDA/energy documents require 7-star/NatHERS, whole-of-home energy, heat pump systems, WELS fixtures, LED lighting and completion report.","quote_item_to_check":"7-star energy, whole-of-home, appliances, glazing, WELS, lighting, SDA certification","risk_level":"High","notes":"Mandatory compliance should not remain an open variation.","bevnol":"Variation Risk","aspire":"Variation Risk","symmetric":"Variation Risk","chet":"Unclear"},{"id":8,"requirement":"Double glazing / glazing spec","source_requirement":"SDA and energy pathway require double glazing; final drawings/energy schedule may require specific glazing performance.","quote_item_to_check":"Double glazing, Low-E, thermally broken frames, window seals","risk_level":"High","notes":"Bevnol excludes Low-E/thermally broken glazing; Aspire has PS; Symmetric has caveat.","bevnol":"Variation Risk","aspire":"Provisional Sum","symmetric":"Variation Risk","chet":"Unclear"},{"id":9,"requirement":"KCE structural design","source_requirement":"Structural drawings/compliance certificate exist and must be priced.","quote_item_to_check":"Slab, footings, steel/LVL beams, bracing, posts, retaining, carport structural items","risk_level":"Medium-High","notes":"Where source docs exist, structural PS items should be challenged.","bevnol":"Unclear","aspire":"Provisional Sum","symmetric":"Unclear","chet":"Included / clearer"},{"id":10,"requirement":"Retaining","source_requirement":"Retaining must suit site levels and structural/civil requirements.","quote_item_to_check":"Retaining wall length, height, footing, drainage and boundary conditions","risk_level":"Medium-High","notes":"Bevnol includes only 7lm; Aspire PS; Symmetric weak.","bevnol":"Included / limited","aspire":"Provisional Sum","symmetric":"Excluded / Unclear","chet":"Unclear"},{"id":11,"requirement":"Driveway / crossover / reinstatement","source_requirement":"External access must be all-weather, drained and completed to council requirements.","quote_item_to_check":"Driveway, crossover, footpath/kerb reinstatement, asset protection","risk_level":"High","notes":"Chet is strongest; Bevnol wording is vague; Aspire owner-side risk.","bevnol":"Unclear","aspire":"By Owner / Excluded","symmetric":"Variation Risk","chet":"Included"},{"id":12,"requirement":"Sewer / service proving and diversion","source_requirement":"Asset/service locations must be proven by hand; diversion/branch/depth and existing dwelling services need fixed-price clarification.","quote_item_to_check":"Sewer diversion, branch alteration, depth >1.5m, existing dwelling continuity","risk_level":"High","notes":"Bevnol has wording conflict; Aspire PS; Symmetric weak detail.","bevnol":"Variation Risk","aspire":"Provisional Sum","symmetric":"Unclear","chet":"Unclear / stronger allowance"},{"id":13,"requirement":"Electricity pit / meter / services","source_requirement":"New/changed service connections on subdivided block must be clarified.","quote_item_to_check":"Electricity pit, group metering, mains switchboard, NBN, water meters, activation fees","risk_level":"Medium-High","notes":"Authority-side fees and owner-provided pits can be material.","bevnol":"By Owner / Variation Risk","aspire":"By Owner / Variation Risk","symmetric":"By Owner / Variation Risk","chet":"Unclear"},{"id":14,"requirement":"Livable housing","source_requirement":"Livable housing requirements include step-free access, door/corridor clearances, sanitary circulation, hobless shower and reinforcement.","quote_item_to_check":"NCC livable housing compliance","risk_level":"Medium","notes":"Should be expressly confirmed by each builder.","bevnol":"Unclear","aspire":"Unclear","symmetric":"Unclear","chet":"Unclear"}],"exclusions":[{"id":1,"builder_slug":"bevnol","item":"Landscaping","status":"Excluded","estimate_low":20000,"estimate_realistic":40000,"estimate_high":70000,"risk_level":"High","source_basis":"Planning/source library occupation and external works obligations.","notes":"Must be priced separately or carried as owner contingency.","builder_name":"Bevnol"},{"id":2,"builder_slug":"bevnol","item":"Internal/external fencing","status":"Excluded","estimate_low":5000,"estimate_realistic":15000,"estimate_high":30000,"risk_level":"High","source_basis":"External works and boundary conditions.","notes":"Could interact with TPZ requirements and neighbour boundary works.","builder_name":"Bevnol"},{"id":3,"builder_slug":"bevnol","item":"Low-E / thermally broken glazing","status":"Excluded / Variation Risk","estimate_low":0,"estimate_realistic":20000,"estimate_high":40000,"risk_level":"High","source_basis":"SDA/energy source obligations; Bevnol exclusion wording.","notes":"Needs direct written confirmation against the final energy report.","builder_name":"Bevnol"},{"id":4,"builder_slug":"bevnol","item":"Driveway/crossover/reinstatement shortfall","status":"Unclear / Variation Risk","estimate_low":5000,"estimate_realistic":20000,"estimate_high":35000,"risk_level":"High","source_basis":"Source library access/crossover obligations and Chet comparative allowance.","notes":"Bevnol's driveway wording is not enough to confirm crossover/reinstatement.","builder_name":"Bevnol"},{"id":5,"builder_slug":"bevnol","item":"Tree/arborist supervision and certification","status":"Excluded / Variation Risk","estimate_low":1500,"estimate_realistic":6000,"estimate_high":20000,"risk_level":"High","source_basis":"TPMP source obligations.","notes":"Tree fencing does not equal full TPMP compliance.","builder_name":"Bevnol"},{"id":6,"builder_slug":"bevnol","item":"Sewer branch/depth/service rectification","status":"Excluded / Variation Risk","estimate_low":5000,"estimate_realistic":15000,"estimate_high":35000,"risk_level":"High","source_basis":"Sewer/service source documents and Bevnol depth limitation.","notes":"Clarify branch alteration and connections deeper than 1.5m.","builder_name":"Bevnol"},{"id":7,"builder_slug":"bevnol","item":"Rock / bored piers / angle of repose","status":"Excluded","estimate_low":0,"estimate_realistic":20000,"estimate_high":60000,"risk_level":"High","source_basis":"Bevnol exclusions and site/structural obligations.","notes":"Conditional risk; do not carry high unless triggered.","builder_name":"Bevnol"},{"id":8,"builder_slug":"aspire","item":"Carport","status":"Unclear / likely missing","estimate_low":15000,"estimate_realistic":30000,"estimate_high":50000,"risk_level":"High","source_basis":"Source drawings show 33.5m2 carport.","notes":"Must be confirmed before treating Aspire as comparable.","builder_name":"Aspire"},{"id":9,"builder_slug":"aspire","item":"Driveway, paving, shed, clothesline, fencing","status":"By Owner / Excluded","estimate_low":30000,"estimate_realistic":70000,"estimate_high":120000,"risk_level":"High","source_basis":"Aspire exclusions and source external works obligations.","notes":"Major owner-side completion cost.","builder_name":"Aspire"},{"id":10,"builder_slug":"symmetric","item":"7-star/NCC 2022 compliance gap","status":"Variation Risk","estimate_low":10000,"estimate_realistic":30000,"estimate_high":60000,"risk_level":"High","source_basis":"Source energy/SDA obligations and Symmetric energy wording.","notes":"Must be repriced against current mandatory requirements.","builder_name":"Symmetric"}],"pcps":[{"id":1,"builder_slug":"bevnol","item":"NBN provisioning","item_type":"PS","amount":2640,"status":"Provisional Sum","risk_level":"Low-Medium","notes":"Owner remains responsible for network connection/activation cost.","builder_name":"Bevnol"},{"id":2,"builder_slug":"aspire","item":"Material handling / crane / traffic management / overhead powerlines","item_type":"PS","amount":36000,"status":"Provisional Sum","risk_level":"High","notes":"Large site constraint allowance that may move.","builder_name":"Aspire"},{"id":3,"builder_slug":"aspire","item":"Double glazing","item_type":"PS","amount":27500,"status":"Provisional Sum","risk_level":"High","notes":"Should be fixed against final energy report if possible.","builder_name":"Aspire"},{"id":4,"builder_slug":"aspire","item":"Reverse-cycle ducted airconditioning","item_type":"PS","amount":18000,"status":"Provisional Sum","risk_level":"Medium-High","notes":"System sizing and final design can change.","builder_name":"Aspire"},{"id":5,"builder_slug":"aspire","item":"Additional structural steel/timber beams and steel posts","item_type":"PS","amount":13000,"status":"Provisional Sum","risk_level":"Medium-High","notes":"KCE structural drawings exist, so request fixed pricing.","builder_name":"Aspire"},{"id":6,"builder_slug":"aspire","item":"Sewer redirect","item_type":"PS","amount":8000,"status":"Provisional Sum","risk_level":"High","notes":"Need fixed price against sewer/service information where possible.","builder_name":"Aspire"},{"id":7,"builder_slug":"aspire","item":"Civil drainage design","item_type":"PS","amount":4000,"status":"Provisional Sum","risk_level":"High","notes":"Approved drainage documents exist; construction scope still needs pricing.","builder_name":"Aspire"}],"risks":[{"id":1,"priority":1,"risk":"7-star / SDA / thermally broken glazing","exposed_builders":"Bevnol, Aspire, Symmetric, Chet confirmation needed","risk_level":"High","likely_cost":"Medium to high","mitigation":"Require written confirmation that final energy report, NCC 2022 and SDA obligations are included as fixed price."},{"id":2,"priority":2,"risk":"Drainage / OSD / WSUD / LPOD","exposed_builders":"Bevnol, Aspire, Symmetric","risk_level":"High","likely_cost":"High","mitigation":"Require itemised drainage inclusion list covering OSD, orifice, pits, pipes, raingardens, LPOD and council inspections."},{"id":3,"priority":3,"risk":"Landscaping and fencing","exposed_builders":"Bevnol, Aspire, Symmetric","risk_level":"High","likely_cost":"$30k-$90k+","mitigation":"Obtain fixed separate price or carry owner contingency."},{"id":4,"priority":4,"risk":"TPMP / arborist / tree protection","exposed_builders":"Bevnol, Aspire, Symmetric, Chet confirmation needed","risk_level":"High","likely_cost":"Medium to high","mitigation":"Confirm project arborist, fencing, ground protection, inspections and final certification."},{"id":5,"priority":5,"risk":"Driveway / crossover / reinstatement","exposed_builders":"Bevnol, Aspire, Symmetric","risk_level":"High","likely_cost":"$10k-$35k+","mitigation":"Require specific scope for driveway, crossover, footpath/kerb reinstatement and asset protection."},{"id":6,"priority":6,"risk":"Sewer diversion / branch / depth","exposed_builders":"Bevnol, Aspire, Symmetric","risk_level":"High","likely_cost":"$8k-$35k+","mitigation":"Confirm branch, depth >1.5m, existing dwelling continuity and service proving."},{"id":7,"priority":7,"risk":"Aspire carport scope gap","exposed_builders":"Aspire","risk_level":"High","likely_cost":"$15k-$50k","mitigation":"Ask Aspire to confirm the 33.5m2 carport is included or provide variation price."},{"id":8,"priority":8,"risk":"Chet labour/subtotal reconciliation","exposed_builders":"Chet","risk_level":"High","likely_cost":"Approx. $87k incl. GST","mitigation":"Request corrected BOQ and subtotal reconciliation before comparing."},{"id":9,"priority":9,"risk":"Structural PS despite available engineering","exposed_builders":"Aspire, Symmetric, Bevnol confirmation needed","risk_level":"Medium-High","likely_cost":"Medium","mitigation":"Ask builders to price from KCE structural drawings rather than broad allowances."},{"id":10,"priority":10,"risk":"Authority/service costs","exposed_builders":"All builders","risk_level":"Medium-High","likely_cost":"Medium","mitigation":"Clarify power pit, water meter, NBN, asset protection, tapping permits and connection activation fees."}],"questions":[{"id":1,"category":"Source-library compliance","question":"Please confirm the quote includes all works required by the architectural drawings, structural drawings, civil/drainage plans, energy/SDA report, soil report, planning permit, TPMP and service documents.","target_builders":"All","priority":"High"},{"id":2,"category":"Energy / NCC","question":"Please confirm full NCC 2022, 7-star NatHERS, whole-of-home energy and livable housing compliance is included as a fixed price.","target_builders":"All","priority":"High"},{"id":3,"category":"Glazing","question":"Please confirm the final window/door glazing specification, including double glazing, Low-E and thermally broken frames if required by the energy report.","target_builders":"All","priority":"High"},{"id":4,"category":"Drainage","question":"Please confirm the approved drainage scope, including rainwater tank, charged downpipes, pits, pipe storage, OSD/orifice, raingardens, LPOD connection, tapping permit/new pit risk and final inspection.","target_builders":"All","priority":"High"},{"id":5,"category":"External works","question":"Please confirm the exact driveway, crossover, footpath, kerb, asset protection, reinstatement, landscaping and fencing scope included in the price.","target_builders":"All","priority":"High"},{"id":6,"category":"Carport","question":"Please confirm whether the 33.5m2 carport shown in the source drawings is included in your price, including slab/base, posts, roof, drainage and finishes.","target_builders":"Aspire, Chet","priority":"High"},{"id":7,"category":"Tree / TPMP","question":"Please confirm project arborist, tree protection fencing, ground protection, inspections, tree-sensitive excavation and final TPMP certification are included.","target_builders":"All","priority":"High"},{"id":8,"category":"Sewer / services","question":"Please confirm sewer diversion, sewer branch alterations, connection depth limits, service proving by hand, existing dwelling service continuity, electricity pit, group metering, water and NBN responsibilities.","target_builders":"All","priority":"High"},{"id":9,"category":"PC/PS","question":"Please provide a complete PC/PS schedule with quantities, allowance amounts, builder margin, and whether each item can be converted to fixed price.","target_builders":"All","priority":"High"},{"id":10,"category":"Chet reconciliation","question":"Please provide the corrected BOQ reconciliation and confirm whether the separate labour cost has been included twice.","target_builders":"Chet","priority":"High"}],"sourceDocuments":[{"id":1,"name":"00741835730252024091013160001.pdf","pages":1,"category":"Property information / council","date_version":"10 Sep 2024","purpose":"Frankston City Council Property Information Certificate, Regulation 51(2)","review_status":"Reviewed"},{"id":2,"name":"15 BAYVIEW ROAD_SDA_28.01.25.pdf","pages":84,"category":"SDA / Energy / WSUD","date_version":"28 Jan 2025","purpose":"Sustainable Design Assessment by Torple Energy Ratings","review_status":"Reviewed"},{"id":3,"name":"15 Bayview Road Frankston.pdf","pages":11,"category":"Soil / geotechnical","date_version":"Report 25389; investigation 22 May 2025","purpose":"Allen Karlovic Soil Engineering site classification report","review_status":"Reviewed"},{"id":4,"name":"15 Bayview Road, Frankston Vic 3199 - TPMP.pdf","pages":27,"category":"Tree / arborist","date_version":"27 May 2025; Version 1","purpose":"Tree Protection Management Plan by TMC Reports","review_status":"Reviewed"},{"id":5,"name":"15 Bayview Road, Frankston Vic 3199 - impact asessment.pdf","pages":30,"category":"Tree / arborist","date_version":"Assessment 16 Sep 2024; report 27 May 2025; Version 1","purpose":"Arboricultural Impact Assessment by TMC Reports","review_status":"Reviewed"},{"id":6,"name":"15 Bayview Road_PRELIM.pdf","pages":5,"category":"Energy / NatHERS","date_version":"8 Sep 2025; output 10 Sep 2025","purpose":"FirstRate provisional diagnostic information, reference EE25-0359","review_status":"Reviewed"},{"id":7,"name":"24-085-Sewer.pdf","pages":3,"category":"Sewer / services","date_version":"23 Sep 2024","purpose":"South East Water asset information combined","review_status":"Reviewed"},{"id":8,"name":"24-085_Bayview_FloodLevel_08426_650_App_Number_76546397.pdf","pages":2,"category":"Flood / Melbourne Water","date_version":"22 Apr 2025","purpose":"Melbourne Water flood level advice","review_status":"Reviewed"},{"id":9,"name":"24-085_Bayview_VICPlan_LP011532_App_Number_76546397.pdf","pages":2,"category":"Title / plan","date_version":"22 Apr 2025 timestamp","purpose":"LANDATA plan LP011532","review_status":"Reviewed; technical/image-based"},{"id":10,"name":"24-085_Bayview_VICTitle_8426_650_App_Number_76546397.pdf","pages":1,"category":"Title / property","date_version":"Produced 22 Apr 2025","purpose":"LANDATA title search, Volume 08426 Folio 650","review_status":"Reviewed"},{"id":11,"name":"24-085bayview_AssetPlan-74183_15_bayview_frankston_App_Number_74183573.pdf","pages":3,"category":"Sewer / services","date_version":"23 Sep 2024","purpose":"South East Water asset information combined","review_status":"Reviewed"},{"id":12,"name":"24-085bayview_AssetPlan_15_bayview_frankston_App_Number_74183573.pdf","pages":2,"category":"Sewer / services","date_version":"11 Sep 2024","purpose":"South East Water property sewerage plan","review_status":"Reviewed"},{"id":13,"name":"25-023-WD-A.pdf","pages":30,"category":"Architectural / working drawings","date_version":"Oct 2025; Issue A; plans for quoting","purpose":"Andrew Ferris Building Design working drawings, Drawing No. 25-023","review_status":"Reviewed"},{"id":14,"name":"25137 Bayview Road Certificate of Compliance.pdf","pages":1,"category":"Structural / compliance","date_version":"7 Oct 2025","purpose":"KCE Certificate of Compliance for proposed structural building work","review_status":"Reviewed"},{"id":15,"name":"25137 Bayview Road Computations.pdf","pages":51,"category":"Structural computations","date_version":"Oct 2025","purpose":"KCE structural computations, reference 25/137","review_status":"Reviewed; technical/image-based"},{"id":16,"name":"25137 Bayview Road Structural Drawings.pdf","pages":8,"category":"Structural drawings","date_version":"Oct 2025","purpose":"KCE structural drawings, reference 25/137","review_status":"Reviewed"},{"id":17,"name":"25148 Bayview Road Detention Computations.pdf","pages":4,"category":"Drainage / OSD computations","date_version":"Oct 2025","purpose":"KCE detention / OSD computations, reference 25/148","review_status":"Reviewed; technical/image-based"},{"id":18,"name":"25148 Bayview Road Drainage Plan.pdf","pages":2,"category":"Civil / drainage drawings","date_version":"Oct 2025; Issue 0","purpose":"KCE drainage design, reference 25/148","review_status":"Reviewed"},{"id":19,"name":"Approval Letter - 15 Bayview Road Frankston VIC 3199.pdf","pages":2,"category":"Civil / drainage approval","date_version":"16 Dec 2025","purpose":"Frankston City Council drainage design construction plan approval","review_status":"Reviewed"},{"id":20,"name":"Approved Drainage Plans - 15 Bayview Road Frankston VIC 3199.pdf","pages":2,"category":"Civil / drainage drawings","date_version":"Dec 2025; Issue 1","purpose":"KCE approved drainage plans, reference 25/148","review_status":"Reviewed"},{"id":21,"name":"Cover letter - Endorsed Plans - 15 Bayview Road, Frankston - 1135 2024 P A.pdf","pages":1,"category":"Planning / endorsed plans","date_version":"29 Sep 2025","purpose":"Frankston City Council cover letter for endorsed plans","review_status":"Reviewed"},{"id":22,"name":"Endorsed Plans - 15 Bayview Road, Frankston.pdf","pages":64,"category":"Planning / endorsed plans","date_version":"Endorsed 29 Sep 2025; Planning Permit 1135/2024/P","purpose":"Council-endorsed architectural/arborist/SDA plan package","review_status":"Reviewed"},{"id":23,"name":"LPOD - 15 Bayview Road, Frankston.pdf","pages":5,"category":"Stormwater / LPOD","date_version":"17 Sep 2024; Application 361/2024/LP","purpose":"Frankston City Council legal point of discharge advice","review_status":"Reviewed"},{"id":24,"name":"Planning Permit - 1135 2024 P - 15 Bayview Road Frankston.pdf","pages":8,"category":"Planning permit","date_version":"16 Apr 2025; Permit 1135/2024/P","purpose":"Frankston City Council planning permit","review_status":"Reviewed"},{"id":25,"name":"STORM Rating Report - Bayview Road.pdf","pages":4,"category":"WSUD / stormwater quality","date_version":"30 Oct 2025; Project 50813B14","purpose":"BlueFactor STORM rating report","review_status":"Reviewed"},{"id":26,"name":"VS3732 - 15 Bayview Road, Frankston - RELOC-A3 H.pdf","pages":1,"category":"Survey / title re-establishment","date_version":"Survey 1 May 2023; plan 10 May 2023","purpose":"VicSurvey title re-establishment survey","review_status":"Reviewed"},{"id":27,"name":"VS3732 - 15 Bayview Road, Frankston - RFL ATTEMPT 2-A1 H.pdf","pages":1,"category":"Survey / feature and level","date_version":"Date not clearly extracted; VicSurvey reference VS3732","purpose":"VicSurvey feature and level survey","review_status":"Reviewed"},{"id":28,"name":"VS3732 - 15 Bayview Road, Frankston - Title & Plan.PDF","pages":4,"category":"Title / plan","date_version":"18 Apr 2023","purpose":"LANDATA imaged title and plan, LP011532","review_status":"Reviewed"}]}